Is your factory roof suitable for solar? What an engineer checks
Structure, condition, waterproofing, shading and access: the checks that decide what your roof can carry.
Most factory roofs can carry a solar plant, but not every part of every roof, and not always in the condition it is in today. The roof decides how much capacity fits, how the modules are fixed and how long the plant lasts without trouble. This guide sets out what an engineer checks, what you can check yourself beforehand, and what to do when the roof falls short.
It gives no load figures, spacings or capacities per square metre. Those come from a structural assessment of your building and cannot be read from a guide.
The roof types and what each one asks for
| Roof | How modules are fixed | What to check first |
|---|---|---|
| Metal sheet on purlins | Rails clamped to the sheet's seams, or fixed through the sheet into the purlins. | The sheet profile, its age and corrosion, and the spare capacity of the purlins and trusses. |
| Concrete (RCC) slab | A structure held down by ballast blocks, or anchored into the slab. | The load the slab can take, the state of the waterproofing and the drainage slope. |
| Asbestos or fibre cement sheet | Not fixed to the sheet. The structure is carried independently on the building's frame, or the sheet is replaced first. | The sheets are brittle and unsafe to walk on. Treat replacement as part of the project. |
| Roof with skylights and vents | As for the roof type, laid out around the openings. | Translucent sheets cannot carry a person. Mark and guard them before any survey. |
What an engineer checks
Structure
A solar plant adds permanent weight and, more importantly, wind load. Wind tries to lift modules off the roof, and that uplift passes through the fixings into the purlins, the trusses and the columns. The check is whether each of those has capacity to spare. It needs the building's structural drawings, or measurements taken on site when drawings do not exist. Buildings designed with little margin, and older buildings that have been altered, are the ones where this check changes the design.
Condition and remaining life
A solar plant is expected to stay in place for decades. A roof sheet with a few years left will have to be replaced underneath it, which means taking the plant down and putting it back. Compare the remaining life of the roof with the life of the plant, and replace or treat the roof first where it is the shorter of the two.
Waterproofing
Every fixing through a sheet is a possible leak, and every anchor in a slab passes through the waterproofing layer. Ask how each penetration is sealed, who is responsible for a leak afterwards, and whether the roof's existing warranty survives the installation.
Shading and usable area
Parapets, water tanks, chimneys, neighbouring buildings and trees shade parts of a roof for part of the day. Shaded modules pull down the output of the modules connected with them. The usable area is what is left after shaded zones, walkways, skylights, vents and the setbacks from the roof edge are taken out. It is always less than the roof's area on the drawing.
Orientation and slope
A pitched metal roof fixes the direction and tilt of the modules. Slopes facing away from the sun at midday generate less, and the yield estimate should show each slope separately. A flat slab lets the designer choose the tilt, at the cost of wider spacing between rows.
Access and safety
People will be on this roof for the life of the plant, to clean modules and to maintain equipment. A suitable roof has a safe way up, edge protection or anchor points, and walkways that keep feet off fragile sheets and off the modules.
What comes out of the roof
Exhaust from furnaces, boilers, paint booths and dust collectors settles on modules and can corrode them. Note every vent and stack and what it discharges. Modules are kept clear of them, and the cleaning plan allows for the fouling that remains.
The electrical route
The roof also has to connect to the factory. The check covers where the inverters will stand, how cables come down, the distance to the panel where the plant connects, and whether that panel has the capacity and the space for it.
Lightning and earthing
A plant on a roof changes what a lightning strike meets first. The design should say how the module frames and structure are earthed and how the building's lightning protection is extended to cover the plant.
What you can check before anyone visits
- Find the structural drawings of the building, and the name of the firm that designed or built it.
- Note the age of the roof sheet or the waterproofing, and any leaks or repairs.
- List the skylights, vents, stacks, tanks and other equipment on the roof.
- Note which neighbouring buildings or trees stand higher than the roof.
- Record how people reach the roof today.
- Take photographs from the roof and from the ground, without walking on fragile sheets.
- Ask whether the building's insurance sets conditions for rooftop equipment.
When the roof is not suitable
A roof that fails the checks does not end the project. The usual routes are these.
- Strengthen or replace. Re-sheet the roof or strengthen the purlins, and treat that cost as part of the solar investment.
- Use the parts that pass. A smaller plant on the sound sections of the roof.
- Look off the roof. Parking sheds, a ground-mounted plant on spare land inside the premises, or an elevated structure over a yard.
- Generate elsewhere. In Delhi, Virtual Net Metering lets a consumer take credit for a plant built at another location in the same distribution area; see our guide to the rules. In other states, open access may serve the same purpose for larger consumers.
Questions to ask an installer about your roof
- Who carried out the structural check, and may we see the calculation?
- What wind speed is the mounting structure designed for, and to which standard?
- How is each roof penetration sealed, and who answers for a leak?
- Which parts of the roof did you leave out, and why?
- How will people reach and move around the plant safely?
- What happens to the plant when the roof sheet needs replacing?
Where Sunmaster stands
Sunmaster, a brand of Saev Private Limited (Saev P Ltd), builds rooftop solar plants on working factories. Our case study of two factory rooftops in Delhi describes what that work involves.
Related pages
- Factory solar feasibility: what to prepare and what to expect back
- CAPEX or PPA: how to choose the way you pay
- Solar plant underperforming? How to diagnose it
- Industrial and commercial solar EPC
This guide is general information, not a structural assessment. Have a qualified structural engineer assess your building before any equipment is placed on its roof.
Common questions
Can solar be installed on an asbestos sheet roof?
Not on the sheets themselves. Asbestos and fibre cement sheets are brittle, cannot be walked on safely and should not be drilled. The practical routes are to replace the sheets with metal sheets before the plant is installed, or to carry the solar structure independently on the building's frame so that no load rests on the sheets. Either way, the roof work is part of the project and has to be costed with it.
Will a solar plant make my roof leak?
It should not, if the fixing method suits the roof. Clamps on a standing-seam sheet make no holes at all. Fixings that pass through a sheet are sealed and placed on the crest of the profile, away from where water runs. On a concrete slab, a ballasted structure avoids penetrations. Ask the installer to state in writing who is responsible for a leak at a fixing point.
How much of my roof can be covered with modules?
Less than its full area. Shaded zones, skylights, vents, walkways for maintenance and setbacks from the roof edge all come out first. The figure for your building comes from a layout drawn on a measured plan of the roof, not from a rule of thumb.
Do I need a structural engineer's certificate?
You should have one. The certificate records that a qualified engineer has checked the building for the added weight and wind load. Lenders and insurers often ask for it, and it is the document you will want if the roof is ever damaged in a storm.