Solar plant underperforming? How to find where the energy is going

Establish whether the loss is real, then trace it from the plant to the inverter, the string and the module.

A solar plant that generates less than expected is losing money every day, and the cause is usually findable. The work is to establish first whether the plant is really underperforming, and then to narrow the loss down from the whole plant to an inverter, a string and a module. This guide follows that order.

It gives no loss percentages or target figures. What is normal depends on the site, the season and the equipment, and the right benchmark for your plant is its own design estimate and its own history.

First, is it really underperforming?

Generation falls and rises with the weather, so a low month proves nothing by itself. Three comparisons separate a real problem from a cloudy one.

  1. Against the sunshine received. Divide the energy generated by the energy the sun delivered to the modules in the same period. This is the performance ratio, and it removes the weather from the comparison. It needs irradiance readings from a sensor on site, or satellite data for the location when there is no sensor.
  2. Against the design estimate. The yield report prepared before the plant was built gives expected generation for each month. Compare month with month, not month with annual average.
  3. Against itself. Compare each inverter with the others, and this year with the same months of earlier years. A plant ages slowly and evenly. A sudden change, or one inverter falling behind its neighbours, points to a fault.

Check the measurement as well. A meter read on different dates, an export limit set by the distribution company, or a monitoring gap that hides a week of data can each look like a loss that is not there.

Where the energy goes

CauseWhat it looks like in the dataHow it is confirmed
SoilingOutput drifts down between cleanings and recovers after rain or washing.Compare a freshly cleaned string with its uncleaned neighbour.
ShadingA dip at the same hours each day, changing with the season.Inspect at those hours for new structures, tree growth or self-shading between rows.
Inverter downtimeZero output from one inverter while others run, or late starts and early stops.Read the inverter's event and fault log.
Grid outages and voltage tripsAll inverters stop together, often at the same times of day.Match the stops against the outage record and the inverter's grid fault codes.
String faultsOne inverter input, or one inverter, steadily below its peers.Measure string voltage and current; check fuses, connectors and cables.
Module defectsA slow decline in particular strings that cleaning does not restore.Thermal imaging and current-voltage curve tracing of the suspect strings.
Clipping or export limitsA flat top on the daily output curve at midday.Compare with the inverter rating and any limit set in the controller or by the approval.
High temperatureLower output on hot, clear days than on cool, clear days.Expected behaviour; check that the design estimate allowed for it and that modules are ventilated.
Monitoring faultsGaps, frozen values or totals that disagree with the energy meter.Reconcile the monitoring total with the billing meter for the same period.

A diagnosis in order

  1. Reconcile the meters. Confirm that the monitoring system and the billing meter agree. If they do not, fix the data before drawing conclusions from it.
  2. Account for lost hours. From the inverter logs, total the hours each inverter was off and the reason. Downtime is the simplest loss to find and often the largest.
  3. Compare inverters. Divide each inverter's energy by the module capacity connected to it. Inverters on the same roof should sit close together. Follow the one that does not.
  4. Compare strings. Within the weak inverter, compare string currents on a clear day around noon. A string well below the others has the fault.
  5. Inspect on site. Walk the weak strings. Look for dirt, shade, bird droppings, cracked glass, discoloured cells, burnt connectors, loose cables and damaged junction boxes.
  6. Test. Thermal imaging finds hot cells, failed bypass diodes and heating connectors. Current-voltage curve tracing shows whether a string behaves as its datasheet says. Insulation resistance testing finds cable and earth faults.
  7. Fix, then measure again. Record the performance ratio before and after each repair. The record shows which repair was worth making and supports any warranty claim.

Records worth keeping

  • The design yield report and the as-built drawings, with the string layout
  • Commissioning test results for each string
  • Monthly generation by inverter, with the billing meter reading
  • Irradiance data, where a sensor is fitted
  • A log of cleaning dates, outages, faults and repairs
  • Module and inverter serial numbers, with their warranty documents

A plant with these records can be diagnosed in days. Without them, the first task is to rebuild them.

When it becomes a warranty matter

Module makers warrant that output will not fall below a stated level over the warranty period, and inverter makers warrant the equipment against defects. An installer may also have committed to a level of generation or performance ratio in the contract. A claim under any of these needs evidence: test results from a recognised method, serial numbers, and proof that the plant was cleaned and maintained as the terms require. Read the terms before testing, so that the tests you pay for are the ones the manufacturer accepts.

Questions to ask your maintenance contractor

  1. What was the performance ratio last month, and how was irradiance measured?
  2. How many hours was each inverter unavailable, and why?
  3. Which strings are weakest, and what has been done about them?
  4. When were the modules last cleaned, and what did generation do afterwards?
  5. When was the last thermal inspection, and what did it find?
  6. Do the monitoring totals agree with the billing meter?

Where Sunmaster stands

Sunmaster is a brand of Saev Private Limited. Solar Care takes on plants built by Sunmaster and plants built by other contractors. The Solar Care page describes the service.

Related pages

This guide is general information. Electrical testing on a solar plant involves live DC circuits and work at height, and should be carried out by trained people with the right equipment.

Common questions

How do I know whether my solar plant is underperforming?

Compare its generation with the sunshine it received, with the design estimate for the same month, and with its own earlier years. A plant that is low on all three, or one inverter that is low against its neighbours, has a problem worth investigating. A single low month in cloudy weather does not.

What is performance ratio?

Performance ratio is the energy a plant actually delivered divided by the energy it would have delivered with no losses at all, given the sunshine that reached the modules. Because it is measured against the sunshine received, it stays comparable between a clear month and a cloudy one, which raw generation does not.

How often should solar modules be cleaned?

As often as the dirt on your site requires, which differs between a dusty industrial area and a clean one, and between the dry season and the monsoon. The reliable way to set the interval is to watch how quickly generation falls after a cleaning and how much it recovers after the next one, and to clean when the energy lost costs more than the cleaning.

Can a plant built by another company be diagnosed?

Yes. The work starts from the plant's drawings, commissioning records and generation history, and where those are missing the first step is to rebuild them from a site survey. The equipment warranties stay with the manufacturers whoever maintains the plant.

Is your plant generating less than it should?

Send us your monthly generation, the plant capacity and the inverter make. We will tell you where to look first.

Talk to our team →